Waterproofing to Substructure

  1) Rubberized Bitumen paint waterproofing (2 coats) , horizontal and vertical sides of footing , neck columns , soild block , tie beam and all concrete contact with soil from outside.




2) one layer 4mm Thick water proofing membrane to horizontal and vertical sides .




3)  3.2 mm Thick protection board to all vertical concrete sides contact with the soil .


1 comment:

  1. This is such a great resource that you are providing and you give it away for free. I love seeing blog that understand the value. Im glad to have found this post as its such an interesting one! I am always on the lookout for quality posts and articles so i suppose im lucky to have found this! I hope you will be adding more in the future... shower